Midway Substation

Fall River Electric's bid to site a substation between Driggs and Victor.

7 articles


Growth & Land Use

Teton County Puts Off a Midway Substation Decision as All Three Commissioners Voice Doubts

October 27, 2026

Teton County commissioners closed the Midway substation hearing without a vote and sent the competing studies to staff. All three voiced doubts.

DRIGGS — Teton County commissioners closed the public hearing on Fall River Electric's second Midway substation application Monday without deciding it. They sent the competing technical studies to the county's planning administrator to compare first, and set no date to finish.

The board denied the first application 2-1 in March, with Commissioners Dan Powers and Ron James in the majority, and Chair Brad Wolfe dissenting. It found the substation incompatible with the surrounding homes and its impacts beyond mitigation. Fall River refiled the Midway substation on the same parcel near 700 W. 3500 S. in August, adding a wildlife assessment and 4.25 acres of permanent open space. The county Planning and Zoning Commission recommended approval 4-3 on Sept. 8.

Taylor Cook of Nelson Engineering presented for Fall River. "The substation must be centrally positioned between Victor and Driggs," he said. "If it were too far south, it could not effectively back up the Driggs substation. If too far north, it cannot effectively back up the Victor substation." The Bonneville Power Administration line runs along the parcel's west boundary, and the substation would connect directly to it.

Claire Pincock of MD Acoustics, who prepared Fall River's noise and EMF studies, and Sarah Taubitz of Altitude Acoustics defended the noise survey. Doug Bell of Cavanaugh Tocci Associates, the consultant the neighbors hired, told commissioners the substation would produce "an audible hum that will be observed by the neighbors almost on a continuous basis."

More than 20 people spoke against the Midway substation, and a handful spoke for it. Victor Public Works Director Cole Pendell, speaking for the city, said, "Reliable electrical service is essential to the continued operation of our municipal water and wastewater systems." Anna Trentadue, the attorney for two neighbors whose land adjoins the site, asked the board to have staff analyze the studies the neighbors had submitted, which she said the staff report had not factored in, "unless you choose to just outright deny this entirely, which would also be appropriate."

In March, the board's written decision recorded that Wolfe "felt he could support approval of the application if there was a way to adequately mitigate visual impacts and noise." Opening deliberation Monday, he called Trentadue's request "not a bad idea" and asked whether anyone remembered Spock's line that "the needs of the many outweigh the needs of the few." He went on: "I just want to be very sure … we aren't asking too much of the few, and it seems like we might be." He described himself as undecided: "When one side talks, I go, yeah, they're right. And then the other side talks, I go, yeah, they're right. That to me says I need more information."

When a utility has to buy pricier land, "I assume rates go up," Wolfe said. Spreading a small increase across all of the cooperative's members, he said, "shares the cost instead of just one area."

The 30 or so people who live nearby, Powers said, "are being asked to bear the burden of that development," meaning growth the county has approved. "They want to keep living there, and it's just hard for me to imagine how this is going to be compatible with that." He called Fall River's service "incredibly reliable" and said he applauds the land it set aside along the creek for wildlife. "I am concerned that there isn't room for growth here," he said. The wildlife plan had to meet "a 2-to-1 ratio" of protected land to disturbed land. "But what if they need to impact another acre? Is there another 2 acres that they have available to mitigate? … We're not future-proofing this."

Read full story

DRIGGS — Teton County commissioners closed the public hearing on Fall River Electric's second Midway substation application Monday without deciding it. They sent the competing technical studies to the county's planning administrator to compare first, and set no date to finish.

Read full story
The Week Ahead

Teton County Commissioners Monday: The Midway Substation, Two Subdivisions, and a Budget Opening

October 24, 2026

Teton County commissioners take up 36 items Monday, Oct. 26: the Midway substation hearing, two subdivisions, a budget opening, and final tax rates.

Growth & Land Use

Fall River Refiles the Midway Substation on the Parcel It Was Denied

September 3, 2026

Teton County denied the Midway Substation because its impacts could not be mitigated. Fall River has refiled on the same parcel, offering more mitigation.

Growth & Land Use

Fall River's Midway Substation: Industrial Lots or the Denied Site

July 15, 2026

Fall River wants its Midway Substation on residential land it was denied, and told Teton County it passed on a nearby industrial parcel over price.

Growth & Land Use

Fall River Withdraws Midway Substation Reconsideration

May 30, 2026

Fall River withdrew its Midway Substation reconsideration on May 27, saying the original SUP application was missing a county-required wildlife study.

Growth & Land Use

Midway Substation Returns to Teton County June 8 With New Mitigation and a Narrow Legal Test

May 27, 2026

Fall River seeks reconsideration of its Midway Substation denial. The June 8 hearing pits a stronger project against a narrow legal test.

Growth & Land Use

Teton County Denies Midway Substation Permit

March 23, 2026

Teton County commissioners voted 2-1 to deny Fall River Electric's Midway Substation permit between Driggs and Victor. The cooperative may appeal.


Member of LION Publishers

The Valley Signal

Independent journalism for Teton Valley

Coverage

  • Government & Accountability
  • Growth & Land Use
  • Health & Safety

Newsroom

  • About
  • Feed
  • Join
  • Open Books
  • Standards

Join

A better-informed valley

Get the newsletter free, or become a member and keep every story free for everyone.

Join

© 2026 Valley Signal LLC · Victor, Idaho

Terms of Service · Privacy Policy