Driggs staff report, wastewater plant 60% design action item
City of Driggs · · Staff report
Originally published by City of Driggs: the original, as we copied it June 30, 2026.
We took out 9 addresses, 6 phone numbers and 6 email addresses. How we redact
What's in it
- Public Works Director Jay T. Mazalewski wrote the report to the Driggs City Council for its June 2, 2026, meeting, asking the council to decide how large the wastewater treatment plant expansion should be.
- The background traces the December 2023 facility plan, the April 2024 design contract with Forsgren Engineering, the 60% design submitted in February 2025, and Victor's March 28, 2025, notice of termination, after which the council had Forsgren redesign the plant for Driggs flows only.
- It states the redesign moved the expected completion to February 2030, the date the EPA and Department of Justice require the upgraded plant to be online and compliant, and that the inter-city agreement runs through September 30, 2031.
- The council was given two options: a Driggs-only plant, which would need a legal document from Victor that it will be physically disconnected by February 2030, or a return to the earlier design sized for 20-year flows from both cities.
- The report lists questions for the council on each option, including the compliance timeline, costs and their split between the cities, ratepayer protection, legality, fines and funding.
- Attached is a May 22, 2026, letter from DEQ Senior Water Quality Engineer Tyler Ayers rescinding DEQ's May 15, 2026, approval of the preliminary engineering report and 60% design (DEQ No. 25-09-41) for inadequate demonstrated capacity, and asking Driggs to revise the report for combined flows or document that it will not have to serve Victor.