Pinnacle Peak public record

Comments due Nov. 30, 5 p.m.

Have your say

The city’s review of Pinnacle Peak, and the developer’s answers

On Nov. 19, 2026, the city received the developer’s answers to its engineer’s and fire district’s review, with a revised plat, renderings and new water and sewer reports (response worksheet). The draft development agreement was not revised. The Planning and Zoning Commission’s hearing on the plat is 7 p.m. Monday, Dec. 7 (hearing notice).

Water and sewer

  • The developer’s engineer lists no spare water capacity: “Available ERUs Before Required Upgrades: 0.” Its July report had left those figures to the city’s study (Nov. 18 water report, p. 3; July report, p. 3).

  • No connections until new water rights and a well, and all three phases need the city’s new tank.

    Asked: city engineer, “Required capacity must be available before connections are released” (review, W06, p. 3).

    Answer: “no connections can be made until additional water rights are received and a well is installed”; “All phases require this new storage tank” (worksheet, W04 and W06, p. 8). Conceded

  • No water rights mitigation plan yet. Ordinance 2026-09, adopted Sept. 30, requires mitigation to be complete before a final plat is recorded, a building permit issues or a conditional use permit gets final approval, or by a later date set in a council-approved development agreement (Ordinance 2026-09, § 7).

    Asked: city engineer, a mitigation plan “under the adopted ordinance” (review, W02, p. 3).

    Answer: it “will be provided upon receipt of the City’s adopted ordinance” (worksheet, W02, p. 7). Deferred

  • Sewer: the new report lists 88 units available before upgrades, in place of the July report’s 386, and says Phase 3 passes them and needs a new aerator. (Nov. 18 sewer report, pp. 3-4; July report, p. 3)

    Asked: city engineer, set the developer’s share of city sewer improvements “in the development agreement” (review, S07, p. 2).

    Answer: “The DA won’t be signed until the Final Plat is recorded. We have time to resolve this issue” (worksheet, S07, p. 6). Deferred

  • Water and sewer lines would run outside city limits, and the code limit on that is unresolved. (water report, p. 2; sewer report, p. 2)

    Asked: city engineer, “Resolve the restriction on water-main extensions outside City limits under Section 7-1-7(B)” (review, G01, p. 5).

    Answer: “Developer has active application of additional annexations for surrounding properties” (worksheet, G01, p. 12). Not answered

A question a comment could raise

The city engineer asked that the developer’s share of city sewer improvements be set in the development agreement; the developer answered that “The DA won’t be signed until the Final Plat is recorded.” A comment could ask whether the agreement should set that share, with dates and phase limits, before the commission acts on the preliminary plat. Written comments are due by 5 p.m. Monday, Nov. 30 (hearing notice).

Write a comment about water and sewer Read the comment guide

Land use

  • The draft development agreement was not revised; the city’s folder still holds the Oct. 9 draft. (draft development agreement)

    Asked: city engineer, use its review to set “improvements, costs, phasing, water mitigation, maintenance, deadlines, security, and acceptance” (review, G04, p. 5).

    Answer: “Ongoing coordination and discussion will continue to finalize the development agreement” (worksheet, G04, p. 13). Deferred

  • Rail Trail easements: the planner says the developer should get them first; the answer puts them on the city. No document says who pays for the Highway 33 and Egbert Lane fallback.

    Asked: planner, “that the Developer obtain the required Rail Trail easements before the subdivision proceeds” (memo, p. 7; items 14 and 16, p. 3).

    Answer: “City is responsible for coordination and obtaining necessary easements and permits for crossing Rails-to Trails. If not secured, access from Hwy 33 and Egbert Ln will be required” (worksheet, G02, p. 12). Not answered

  • Fire access in the R-3 area and the Lincoln Lane paving deadline are left for later.

    Asked: fire district, turnarounds and a second access (items 17-19, worksheet pp. 3-4); city engineer, a paving deadline (review, T05, p. 4).

    Answer: “Will revise at the R-3 annexation land during the subdivision submittal phase”; “City and Developer to establish in development agreement paving deadline” (worksheet, pp. 3, 11). Deferred

  • Done as asked: two park lots go to the city, down from four (revised plat, sheet 1; Oct. 9 plat); the roundabout is removed and the mailbox moved out of the park (worksheet, pp. 7, 11); a 10-foot pathway is added (sheet 2); townhouse renderings are added (renderings, pp. 18-19); and pressure irrigation is “OWNED AND MAINTAINED BY THE HOA” (plat note 11). Delivered

Baseball resort

  • Fire access to the sports complex is deferred to annexation.

    Asked: fire district, a second access and emergency access to all fields (items 13 and 14, worksheet p. 3).

    Answer: “Second access to the North is planned. To be addressed during annexation phase” (worksheet, p. 3). Deferred

Housing and affordability

Questions the filing didn’t answer

The worksheet answers the fire district and the city engineer, not the planner’s Nov. 16 memo. These planner items have no written answer:

  • Sidewalks with the Perry Avenue paving, on “the city’s Safe Routes to School network” (item 15)
  • Lucas Lane, “proposed to be built only half in the subdivision and city limits” (item 18)
  • “It is recommended that Asher Park Ln connect to Lucas Ln in Phase 1” (item 19)
  • The pedestrian-corridor pathway “with a connection to Lucas Ln in Phase 1” (item 32)
  • “connections to the Rail Trail at 3 separate locations” (item 33)
  • “When will the townhouse lots be condominiumized?” (item 37)

The new documents

The Documents page lists the records this site cites.